PLA Market Survey - Missile Defense Agency (MDA) Ground Test Facility Infrastructure (GTFI), Redstone Arsenal, AL
Agency: | |
---|---|
State: | Alabama |
Level of Government: | Federal |
Category: |
|
Opps ID: | NBD00159792789903810 |
Posted Date: | Feb 20, 2024 |
Due Date: | Mar 5, 2024 |
Source: | Members Only |
- Contract Opportunity Type: Special Notice (Original)
- All Dates/Times are: (UTC-06:00) CENTRAL STANDARD TIME, CHICAGO, USA
- Original Published Date: Feb 20, 2024 03:34 pm CST
- Original Response Date: Mar 05, 2024 04:00 pm CST
- Inactive Policy: 15 days after response date
- Original Inactive Date: Mar 20, 2024
-
Initiative:
- None
- Original Set Aside:
- Product Service Code: Y1JZ - CONSTRUCTION OF MISCELLANEOUS BUILDINGS
-
NAICS Code:
- 236220 - Commercial and Institutional Building Construction
-
Place of Performance:
Redstone Arsenal , AL 35898USA
This is a SPECIAL NOTICE. No proposals are being requested or accepted with this notice. The Corps of Engineers Mobile District is soliciting comments from the construction community addressing the mandated use of Project Labor Agreements (PLA) for large scale construction projects (exceeding $35 million) within the Redstone Arsenal, AL and the surrounding area. This market survey is being posted for the construction of the Missile Defense Agency Ground Test Facility Infrastructure (GFTI).
Description of Work:
The U.S. Army Corps of Engineers, Mobile District, anticipates conversion of approximately 163,466 SF of existing administrative space in Von Braun IV on Redstone Arsenal to data center; Research, Development, Testing and Engineer (RDT&E) laboratories; and updated administrative space for the Missile Defense Agency (MDA) Missile Defense System (MDS) mission. The existing facility is a five-story reinforced concrete and structural steel building on concrete footings, pre-cast wall panels, and build-up roofs. Required functional areas include RDT&E laboratory space, data center/computer operations, administrative space, meeting rooms, access control, break rooms, and storage areas. New construction includes a 1,722 SF exterior stairwell and a 14,138 SF one-story building expansion to house electrical gear for the new data center. Supporting facilities includes high efficiency mechanical systems, electrically driven chillers, fire pumps, electrical supply and distribution, and uninterruptable power supplies and standby generators for mission critical loads. The project also includes domestic water, sanitary sewer, storm drainage, electrical substation modifications, primary power transmission, natural gas and electrical services, fire protection and alarm systems, connectivity to telecommunications network and distributed service, modification of utility yard access roads, chilled water distribution, physical security, new mechanical and electrical equipment yards, and other site improvements. Accessibility will be provided in accordance with ADA-ABA guidelines. Antiterrorism force protection measures include building standoff distances, lighting, bollards, control gates and berms.
A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f).
1) Do you have knowledge that a PLA has been used in the local area on projects of this kind? If so, please provide supporting documentation.
2) Are you aware of skilled labor shortages in the area for those crafts that will be needed to complete the referenced project? If so, please elaborate and provide supporting documentation where possible.
3) Are you aware of time sensitive issues/scheduling requirements that would affect the rate at which the referenced project should be completed? If so, please elaborate and provide supporting documentation where possible.
4) Identify specific reasons why or how you believe a PLA would advance the Federal Government’s interest in achieving economy and efficiency in Federal procurement.
5) Identify specific reasons why you do not believe a PLA would advance the Federal Government’s interest in achieving economy and efficiency in Federal procurement.
6) Identify any additional information you believe should be considered on the use of a PLA on the referenced project.
7) Identify any additional information you believe should be considered on the non-use of a PLA on the referenced project.
(ii) The information gathered in this exercise should include the following information on projects completed in the last 2-5 years (or other timeframe, as appropriate):
1) Project Name and Location
2) Detailed Project Description
3) Initial Cost Estimate vs. Actual Final Cost
4) Was the project completed on time?
5) Number of craft trades present on the project
6) Was a PLA used?
7) Were there any challenges experienced during the project?
Interested Offerors shall respond to this Special Notice no later than 1600 CST, Friday, 5 March 2024. E-mail your response stephanie.m.scalise@usace.army.mil. This Special Notice is not to be construed as a commitment by the Government, nor will the Government pay for the information solicited.
- KO CONTRACTING DIVISION 109 ST JOSEPH ST
- MOBILE , AL 36628-0001
- USA
- Stephanie M. Scalise
- Stephanie.m.scalise@usace.army.mil
- Kyle Rodgers
- Kyle.M.Rodgers@usace.army.mil
- Feb 20, 2024 03:34 pm CSTSpecial Notice (Original)
- Sep 30, 2023 10:55 pm CDT Sources Sought (Original)
TRY FOR FREE
Not a USAOPPS Member Yet?
Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.