Description:
|
The Work includes the construction of improvements for the existing Digester 3 and the existing biosolids dewatering facility including installing a new Digester 3 pump mixing system and appurtenances, rerouting the existing Digester 3 supernatant pipe, installing one new screw press system and appurtenances, modifying the existing dewatered cake horizontal conveyor to tie into the new screw press system, and other miscellaneous and related work as shown on the plans and specifications for the project.
|
Publication Date/Time:
|
11/2/2022 12:00 AM
|
Closing Date/Time:
|
12/7/2022 11:00 AM
|
Bid Opening Information:
|
12/07/2022
|
Pre-bid Meeting:
|
11/15/2022
|
Contact Person:
|
Scott Parker
Carollo Engineers
(916) 565-4888
|
Download Available:
|
ciplist.com
|
Miscellaneous:
|
A mandatory pre-bid meeting will be held at the project site (White Slough WPCF) at 10:00 a.m. on Tuesday, November 15, 2022. Only bidders attending the meeting will be allowed to submit a bid proposal for the project.
|
|