The Project will involve the following: General construction at the City of Iowa Wastewater Treatment Plant, 4366 Napoleon Street SE, Iowa City, IA. Work will include demolition of three existing belt filter presses, procurement and installation of three new belt filter presses with associated modifications of floor slab, mechanical piping and electrical systems, conversion of two window sets to coil doors, replacement of three belt filter press feed pumps and associated piping, replacement of four polymer pumps; replacement of HVAC exhaust fans.

Project Schedule Information:

Milestone 1 Date: January 12th, 2018
Substantial Completion Date: May 1st, 2018
Specified Completion Date: May 31, 2018
Specified Start Date: November 2, 2017
Liquidated Damages: $500 per day

Date plans available:
Wednesday, September 20, 2017
Obtain from:

Stanley Consultants, Inc.
225 Iowa Avenue
Muscatine, IA 52761
563-264-6657

Pre-bid Conference:

Date: September 28, 2017
Time: 10:00 a.m.
Location: Wastewater Treatment Facility, 4366 Napoleon Street SE, Iowa City, Iowa

Project Status
Current
Engineer's Estimate
$1,790,000
Bid Deadline
Tuesday, October 10, 2017 - 2:30pm
Contact
Senior Civil Engineer
319-356-5436

TRY FOR FREE

Not a USAOPPS Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >