CITY OF ST. LOUIS
BOARD OF PUBLIC SERVICE
REQUEST FOR QUALIFICATIONS FOR
PROFESSIONAL ENGINEERING SERVICES
FOR
TRAFFIC MANAGEMENT ENHANCEMENTS, PHASE 6
Dr. MLK Drive (Hodiamont to Grand)
CMAQ-9901(699)
PURPOSE
The City of St. Louis, Board of Public Service (“BPS”), is seeking Statements of Qualifications
(“SOQ”) from firms interested in providing professional engineering services for roadway
infrastructure improvements. The proposed improvements are primarily intended to improve
traffic flow, and therefore reduce travel time, fuel consumption, and vehicular emission output,
along Dr. Martin Luther King Jr. Drive.
I. PROJECT DESCRIPTION
Proposed improvements will include signal upgrades and/or enhancements, fiber optic
interconnect, traffic monitoring cameras, signal timing and optimization, system integration
with the City’s Real-Time Transportation Intelligence Center (TIC), and sidewalk
improvements as needed for ADA compliance. The project will be generally located along the
Dr. MLK Drive corridor, from Hodiamont Avenue to Grand Boulevard, a distance of
approximately 3.75 miles. Additional improvements outside of the Dr. MLK Drive corridor
may be necessary to provide connectivity to the TIC and redundancy to the City’s fiber optic
network.
II. PROJECT FUNDING AND BUDGET
The total estimated cost of improvements is $2,984,000.00, the price of which includes
design, right-of-way acquisition, construction, construction management, and testing. The
funding for this project is provided through local funds and the Congestion Mitigation & Air
Quality Improvement Program (CMAQ).
III. SCOPE OF SERVICES
The City will require professional engineering services for both preliminary engineering and
construction engineering; including, but not limited to, surveying and data collection; the
Page 1 of 10
preparation of right-of-way plans, the preparation of construction documents (plans,
technical specifications, and construction cost estimates); attendance at various meetings
and presentations, assist and provide supporting documentation for the City’s coordination
with affected utilities; shop drawing review; consultant services for construction
engineering (if needed); and post construction traffic reporting.
The Consultant will assist the City as required in obtaining environmental clearances. This
includes, but is not limited to, the Department of Natural Resources Section 4F and/or 106 form to
the Department of Natural Resources, and the Cultural Resources Office (CRO) Section 106
and/or Preservation Board approval process and the Categorical Exclusion to MoDOT.
All work will be constructed within existing City of St. Louis right-of-way. Temporary
construction easements may be required. The Consultant shall provide a design that minimizes the
need for any temporary right-of-way acquisition. Property acquisition, if necessary, will be
administered by others.
IV. DESIGN STANDARDS
The Consultant will ensure that the design work conforms to current industry standards
including but not limited to:
City of St. Louis
Complete Streets Policy defined by Ordinance 69955.
Standard Specifications, Bid Items, and Standard Details for Street and Alley
Construction – latest edition
MoDOT
Engineering Policy Guide
Missouri Standard Specifications for Highway Construction – latest edition
FHWA
Manual on Uniform Traffic Control Devices (MUTCD)
US Access Board
Public Right-of Way Accessibility Guidelines (PROWAG)
NACTO
Urban Street Design Guide
V. SCOPE OF IMPROVEMENTS
The project will update signal equipment and fiber communications along the Dr. MLK
Drive corridor to better manage traffic demand. Proposed improvements include, but are
not limited to, the following:
Page 2 of 10
Replacement of antiquated traffic signal equipment with new conduit/wiring, mast arms,
signal poles, cabinets, controllers, vehicle and pedestrian detection, fiber optic
interconnect, PTZ cameras, and other incidental work necessary for signal operations.
Reconfiguration of the signalization timing to improve traffic flow.
Construction of new ADA and PROWAG compliant pedestrian curb ramps.
Installation of traffic monitoring equipment to assist in monitoring, collecting traffic data,
and incident management from the City of St. Louis Real Time Traffic Management
Center.
Fiber optic cable installation outside of the Dr. MLK Drive corridor as needed to provide
connectivity and redundancy to the City’s existing fiber optic network.
VI. DELIVERABLES
Preliminary construction plans including detour routes, traffic control plans, technical
specifications and construction cost estimate.
Submission of plans to the Metropolitan St. Louis Sewer District (MSD) for permitting
purposes, if required.
Right-of-way plans and associated acquisition documents, if required.
Final construction plans including detour routes, traffic control plans, technical
specifications and construction cost estimate.
Supporting documentation for the City’s coordination with affected utilities.
Answering questions during the bidding process and during construction of the project.
Consultation during construction of the project.
Attendance at various meetings and presentations.
Submittals review and responses to RFIs during construction.
VII. PROJECT SCHEDULE
Task / Activity
Engineering Services Contract Submitted &
Approved to MODOT
Obtain Environmental Clearances (106, CE-2, etc.)
Public Meeting/Hearing
Start
07/2024
10/2024
07/2025
Completion
Deadline
09/2024
03/2025
07/2025
Duration
(months)
3
6
1
Page 3 of 10
Develop and Submit Preliminary Plans
12/2024 03/2025
6
Preliminary Plans Approved
04/2025 06/2025
3
Develop and Submit Right-of-Way Plans
01/2025 06/2025
6
Review and Approval of Right-of-Way Plans
06/2025 08/2025
3
Submit & Receive Approval for Notice to Proceed
for Right-of-Way Acquisition (A-Date)
08/2025 09/2025
1
Right-of-Way Acquisition
10/2025 01/2026
4
Utility Coordination
10/2024 09/2027
36
Develop and Submit PS&E
11/2025 04/2026
6
District Approval of PS&E/Advertise for Bids
05/2026 07/2026
3
Submit and Receive Bids for Review and Approval 08/2026 10/2026
3
Project Implementation/Construction
11/2026 05/2027
12
The above listed schedule is based on the CMAQ grant application. The schedule is subject to
modification.
VIII. REQUIRED QUALIFICATIONS
Consultants interested in submitting a Statement of Qualifications for consideration and
evaluation for providing the services identified in this RFQ shall submit Part II of GSA
Standard Form 330 (SF330) with their SOQ or have a current SF330 Part II on file with the
City of St. Louis, President’s Office, Board of Public Service. (The SF330 Part II is not
included in the total SOQ page count limit).
IX. SUBMITTAL OF STATEMENTS OF QUALIFICATIONS
This Request for Qualification and other related information is available from the City of St.
Louis Bid Express online portal at https://www.bidexpress.com/businesses/20618/home.
SOQs and backup documentation/forms must be submitted to the City of St. Louis through
Bid Express.
The Statements of Qualifications shall include the Consultant, contact person name, firm
name, address, phone and fax number, and e-mail address.
NOTE: The team composition and the identity of the Project Manager included in the
submittal shall not be changed unless the change is submitted and approved by the President,
Board of Public Service.
Note: The City does not permit exclusivity agreements with sub-consultants.
Interested firms shall submit Statements of Qualifications for the type of work outlined above.
SOQ shall be limited to FIVE (5) single-sided 8-1/2” x 11” pages with a minimum font size of
10 (the 5 pages do not include the M/WBE Utilization form, the Unauthorized Alien
Employee Affidavit, or the Signature Sheet of Memorandum of Understanding with
Page 4 of 10
Homeland Security for E-Verify). No other material will be accepted – this includes a cover
sheet or cover letter, copy of certifications, registrations, etc.
If additional information is included in the Statement of Qualifications, it will be removed
from the SOQ before distributing to the Selection Committee members.
Statements of Qualifications must be received no later than 5:00 p.m., FEBRUARY 28,
2024 through the Bid Express online portal at
https://www.bidexpress.com/businesses/20618/home. Submissions will not be accepted after
this time.
The Board of Public Service reserves the right to accept or reject any or all responses, or to
cancel this request in part or in its entirety. All submittals become and remain the property of
the City.
X. QUALIFICATIONS EVALUATION CRITERIA:
The Selection Committee will evaluate each Statement of Qualifications using the following
criteria. Submittal shall be in the same sequential format as follows:
1. Provide examples of five comparable projects that show the experience,
qualifications, and technical competence of the Prime Consultant. The
projects must have been completed within the last ten years and your
company is the designer of record. These projects should be complete or
near completion. Include record of meeting the project schedule, project
budget, construction cost, design fee, and the M/W/DBE goals for these
projects. Provide start and completion dates and references with names,
phone numbers, and e-mail addresses of owner’s representative who is
most knowledgeable of your firm’s performance. Project with incomplete
information will not be considered toward the Prime Consultant’s
experience. Up to five points will be awarded for each applicable project.
(0-25 points)
2. Present experience, qualifications, and technical competence of Project
Manager relative to the five projects described in Item 1 above. List
Project Manager’s experience in managing similar projects within last ten
years if not directly associated with the firm submitting this proposal.
Provide Project Manager’s Professional Registration information including
profession and license# (Do not include copy of license.). Project Manager
shall be a Professional Engineer licensed in the State of Missouri and
shall be currently certified for MoDOT’s LPA Basic Training.
(0-20 points)
Page 5 of 10
This is the opportunity summary page. You are currently viewing an overview of this opportunity and a preview of the attached documentation. For more information, please visit the Publication URL Web page.

TRY FOR FREE

Not a USAOPPS Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >