**Addendum 4 - 10th St and Pine Dr 04-28-23**
Addendum No. 3 Added - 04-27-2023 Bid due date extended to 05/02/2023 @ 2:00PM
Addendum No. 2 - 04-21-2023
Addendum No. 1 - 04-12-2023
The work of this contract consists of the installation of 1,150 linear feet of elliptical concrete stormsewer pipe (38x24 inch), 64 linear feet of 24 inch concrete storm sewer pipe, two Type 13 inlets, 30 tons of asphalt pavement, 41 square yards of concrete pavement; and associated appurtenances. See the construction drawings for additional information.
The Project is to be substantially complete in 46 working days, and finally complete in 53 working days from the date of the Notice to Proceed.