A
general
description of the primary work elements is listed below for reference. Contractor is responsible for reviewing all the drawings and specifications to obtain a complete understanding of the entire work scope. This contract includes all work indicated on the project documents, including but not limited to:
1. Mobilization and establishment of site access and maintenance and protection of existing conditions.
2. Provide general site demolition, salvage, removals, and disposals.
3. Provide and maintain temporary tree protection measures.
4. Provide drain investigation using CCTV and minor cleaning of the existing drainage system
5. Regrade site to meet grades indicated on Grading Plan L-202
6. Supplement and prepare existing synthetic turf base.
7. Replace synthetic turf, shock pad, infill, material, and sewn striping over existing base to remain
8. Replace damaged concrete curb and nailers for synthetic turf.
9. Provide testing of new synthetic turf and correct deficiencies.
10. Replace resilient track surface and asphalt base.
11. Provide striping and markings for resilient track surface and synthetic turf field.
12. Replace missing welded wire fence panel fasteners and tighten all existing fasteners.
13. Remove and replace eight (8) doors, frames and hardware sets.
14. Replace four (4) new signs affixed to bathroom doors
15. Remove two (2) existing vines from fence, panels and plant two (2) new vines.
16. Provide all necessary permits
Add Alternate 1:
1. Repair concrete perimeter wall spalls and cracks along interior side of 47th Avenue as indicated
Add Alternate 2:
1. Remove and replace Cable Mesh Fence along dugout and backstop as indicated.
NYS OPRHP has established the following bid schedule and subsequent work schedule:
First day of Plan Sales 4 Oct 2022
Pre-Bid Meeting 11 Oct 2022
RFI Due Date 18 Oct 2022
Addendum #1 25 Oct 2022
Bid Opening 2 November 2022
Anticipated Notice To Proceed 30 January 2023
Preconstruction Meeting 06 February 2023
Mobilization 09 February 2023
Substantial Completion 17 May 2023
Completion of Physical Work on Site 31 May 2023
|